The build

From survey to swimming

Ten stages. Three to eight weeks of engineering and permit before the first cut, then ten to sixteen weeks on site. Written down here so you can hold us to it.

Engineering
3 to 8 weeks
On site
10 to 16 weeks
Stages
10
Crews
One
  1. 01

    Site visit and survey

    Week 1

    We measure the yard, find the setbacks, easements and the septic or well if there is one, and check what a truck can physically reach. Half of what makes a design work is decided here.

  2. 02

    3D design and revisions

    Weeks 1 to 3

    You see the pool in your own yard, from your own back door, before you commit to anything. We expect two or three rounds of changes. Nobody signs off on a plan view alone.

  3. 03

    Engineering and permit

    Weeks 3 to 8

    Structural engineering, then submission to the county or city. This is the stage nobody can speed up, and any builder who promises otherwise is guessing.

  4. 04

    Layout and excavation

    Day 1 to 3

    The shell is painted on the ground and you approve the position in person. Then the dig, and the spoil leaves the site the same day.

  5. 05

    Steel and plumbing

    Week 1 to 2

    The rebar cage is tied to engineered spacing, then main drains, returns, skimmers and the spa loop go in. Inspected before anything is covered.

  6. 06

    Gunite shell

    Week 2 to 3

    Shotcrete pumped and carved in one day, then cured wet for a week. This is the structure, and it is the part you will never see again.

  7. 07

    Tile, coping and features

    Week 4 to 6

    Waterline tile, coping stone, spa spillway and any sheer descents or scuppers. Precision stage. Slow on purpose.

  8. 08

    Decking and hardscape

    Week 6 to 9

    Base compaction, drainage, then paving. Walls, steps, fire features and the outdoor kitchen shell if one is in scope.

  9. 09

    Interior finish

    Week 9 to 11

    Pebble, quartz or plaster applied and acid-washed, then the fill starts immediately and does not stop until it reaches the tile.

  10. 10

    Startup and handover

    Week 11 onward

    Two to four weeks of brushing and chemistry to bring the finish up properly, equipment and automation walkthrough, then the warranty pack. We stay on your chemistry until it holds.

310+

Pools built in Tampa Bay

17

Years designing and building

1

Crew, start to finish

0

Change orders for our own errors

Common questions

The things people ask at stage three

A engineered gunite pool with a standard finish and a walkway starts around $68,000. Most of what we build lands between $110,000 and $165,000 once a spa, a full deck and gas heat are in scope. Anyone quoting a figure before seeing your yard is quoting a different yard.

Long rectangular pool flanked by two rows of loungers and fringed umbrellas, with tall palm trees against a pale sky at golden hour

Tampa, FL

Tell us about the yard.

Send the address and a photo of the back of the house. That is enough for us to tell you whether what you have in mind is realistic before anyone drives anywhere.

(813) 555-0142Design consult